Main Unit Bundled Items and Unpacking
Bundled Items
| No. | Bundled Items | Qty. |
|---|---|---|
| 1 | Main Unit | 1 |
| 2 | Power cable | 1 |
| 3 | Manual holder | 1 |
| 4 | Cleaning cloth holder | 1 |
| 5 | Ink cartridge cover (for transportation) | 4 |
| 6 | Paper size label | 1 |
Unpacking Procedure
Items to Prepare
- Gloves
- Cutter
Minimum number of workers
3 persons
Caution / 注意 |
Be sure to check the following precautions before unpacking.
|
Unpacking Procedure
Hold the end of the PP band on the looped side and lift it up to remove the two PP bands.

Remove the tape and open the top side.

- Remove the cushioning materials on the top. Be careful not to drop the manual box and AC cable stored in the cushioning material.

- Remove 4 corner angles.

- Remove 2 joints.

- Remove the packing box upwards.

- Peel off the 4 blue tapes that hold the vinyl sheet under the 4-sided body to the Main Unit.

- Remove the plastic bag.

- Remove the cushioning material.

Caution / 注意The cushioning material must be reused for pre-delivery while transporting, so make sure to save it until pre-delivery transporting is complete.
Lift the main unit and remove it from the packing box.

Check Point / チェックポイントHold on the positions shown in the figure when lifting the main unit.

Remove the exterior, internal protective tape, and protective materials.
Caution / 注意This product has three transportation parts required for transportation. When unpacking, be careful not to accidentally throw it away (see below for details).
- Front side/ Right side

- Front side/ Left side

- ADF

- SCN

C1 Cassette

- Front side/ Right side
- Open the Front Cover.
- Remove the protect tape and remove the head shaft transport fixing parts2 (A).

Caution / 注意Do not throw away the head shaft transport fixing parts2 as it will be used for re-transportation.
- Pull out the C1 cassette.
- Install and store the head shaft transport fixing parts2 (A) to the C1 cassette bottom.

Caution / 注意When installing the transport fixing parts for the head shaft to the C1 cassette, press the film (A) against the floor and ensure that it is not deformed.

- Remove the protect tape and remove the head transport fixing parts1 (A) .

- Store the head transport fixing parts1 (A) according to the shape of the hole in the cover.

Caution / 注意Do not throw away the head transport fixing parts1 as it will be used for re-transportation.
- Open the MP Tray (A) and remove the protective tape.

- Close the MP Tray.
- Open the right door unit (A).

- Pull the lever to open the belt unit (A) slightly.

Caution / 注意- Do not touch the belt transport surface of the belt unit.
- Do not remove the protective film shown in the figure below until the tape is removed in the following procedure.

- Remove the protective tape and remove the transport fixing parts for cap.

Check Point / チェックポイントIf the transport fixing parts cannot be removed by pulling the tape, press the lever (A) on the it to remove it.

Caution / 注意Do not throw away the cap transport fixing parts as it will be used for re-transportation.
Install the cap transport parts (A) in the position shown in the Right Door Unit figure.
Align the protrusion (B) and hole (C) when installing it.

- Peel off the 2 tapes and remove the protective sheet (A).

- Close the Belt Unit.
- Close the Right Door Unit.
- Close the front cover.