Floor Bridge Unit B

Bundled Items

No.Bundled ItemsQty.
1Floor Bridge Unit B1
2Screw M3 × 65
Unpacking Procedure
Items to Prepare
  • Gloves
  • Cutter
Minimum number of workers

1 person

Caution / 注意

Be sure to check the following precautions before unpacking.

  • All workers must read the unpacking procedure together before starting the work.
  • Wear easy-to-move clothing, gloves and safety shoes and work with care for injuries etc.
  • Work with sufficient working space.
  • Work in a posture that does not easily apply a load on your body, and stop work immediately if you feel that the load is too large during the work.
Unpacking Procedure
  1. Remove the tape and open the top cover.
  2. Remove the bundled  small bag (A).
  3. Remove the packing material (A).
  4. Remove the floor bridge unit B (A).
  5. Remove the tape (A) and spread the cushioning material.
  6. Remove all the tapes.